Administrative building and warehouse of “WILO” company – KuWatt Mechatronics
“Fire station” type IV for 2 cars
August 20, 2018
Overhaul of the distribution substation 10 kV (RP-10kV)
August 20, 2018

Date: 2017 – 2018

Types of service: electrical work;

low-current networks: SCS, APS

Description of works:
Electric installation work:

installation of in-site electrical networks
installation of power shields (main switchboard, …)
lighting equipment
outlets
switches
cable trays
lightning protection and earthing systems;
Installation of low-current networks:

installation of a structured cabling system (SCS)
installation of automatic fire alarm (APS)